Sasha plans to work on the microscope crate on September 25, 2014. There continues to be a networking issue but Sasha seemed confident that it'll be up and running by the end of the day.
 
Sasha plans to work on the microscope crate on September 25, 2014. There continues to be a networking issue but Sasha seemed confident that it'll be up and running by the end of the day.
 +
 +
On September 25, 2014 the hodoscope counters were removed and the microscope was moved into position. It was placed just after the magnet leg (on the downstream side) and allowed the microscope to be moved into it's correct position. The fibers sit along the focal plane.

Revision as of 12:46, 26 September 2014

As of September 24, 2014, the motors have been lowered so that they are 1mm above the lower limit. This did not provide enough room for the fibers to pass underneath the hodoscope counters. Tom has organized a group to help remove the counters and move the microscope into position. If the microscope is not able to reach the focal plane there is discussion to move the microscope downstream until it can be positioned correctly into the focal plane. This will result in a different energy range but at the present time there's nothing special about any energy range. Hodoscope counters would have to be adjusted to allow the microscope into this new area.

Sasha plans to work on the microscope crate on September 25, 2014. There continues to be a networking issue but Sasha seemed confident that it'll be up and running by the end of the day.

On September 25, 2014 the hodoscope counters were removed and the microscope was moved into position. It was placed just after the magnet leg (on the downstream side) and allowed the microscope to be moved into it's correct position. The fibers sit along the focal plane.