BW November 2018
11/1: After dark box run 1837, I opened the dark box but noticed that the curtain was not closed all the way. There was an opening at the bottom. I closed the dark box and did some more normalization tests for step 21.
11/6: I put the CAMMA User Agreement page in the top right desk drawer in 403.
11/19: We are keeping the KBM in the tall computer rack in P-405. The computers, which will be surplused, can just slide out of the rack.
We need to check the UPS units in the rack in P-403. Some of them are bad. They are either turned off or constantly blinking. The batteries need to be replaced.
Five of the UPS units have bad batteries. They look like two different kinds, but they all say Smart-UPS 3000. I need to find more information to determine which products they are.
Tomorrow I need to ask about the bucket of sand that says KEMICIDE-L and find out whether Andrew can go to JLab.
11/20: I need to arrange the walkthrough at JLab so I can do it on Tuesday and be done with training that day. But I should not call the people listed on the website. I need to ask Richard about it.
11/21: We have 36 Kapton strips that might be all right to use.