Hall D Collimator Cave Shielding

Richard Jones, University of Connecticut
draft 1.0, January 31, 2006
Photon Tagger and Beam Line Working Group, GlueX Collaboration

The collimator cave shielding is divided into structural elements (building walls, surrounding absorber materials) and installed shielding. The dimensions and weight of the primary installed shielding elements shown in the above figure are described in the table below. None of weights listed for beam line elements have included the weight of the tables or other structures that support them.

material outer dimensions total weight
primary collimator tungsten diameter 20 cm
length 30 cm
180 kg
primary sweep magnet iron, copper, lead length 50 cm
width 20 cm
gap height 2 cm
300 kg
primary iron absorber iron width 50 cm
height 50 cm
length 200 cm
4000 kg
primary concrete absorber concrete width 200 cm
height 200 cm
length 100 cm
10000 kg
secondary collimator nickel diameter 20 cm
length 50 cm
140 kg
secondary sweep magnet iron, copper, lead length 50 cm
width 20 cm
gap height 5 cm
300 kg
secondary iron absorber iron width 100 cm
height 100 cm
length 100 cm
8000 kg
secondary concrete absorber concrete width 430 cm
height 250 cm
length 100 cm
27000 kg
lead exit wall lead width 470 cm
height 290 cm
thickness 15 cm
23000 kg

 

Floor Loading Plan

The shielding plan for the Hall D collimator cave has been developed based upon beam line simulations. A range of shielding options were studied in the simulations, and the plan described above was found to be reasonably close to the minimum required to obtain acceptable background conditions in the experimental hall. However it can be seen from the figure that the size of the collimator cave was made somewhat larger than required by this shielding scenario. This was done to leave flexibility for increasing the amount of shielding if experience with real photon beams in the hall shows it to be necessary. In the simulation studies, another configuration was studied that had substantially more iron in the cave. This so-called heavy shielding option required more space along the beam line and increased somewhat the load on the floor. The heavy shielding option was compared with the moderate shielding configuration described above and was shown to result in modest background reductions. Nevertheless it was deemed prudent to maintain enough space and floor load capacity so that the heavy-shielding option could be exploited if background conditions in the hall prove it to be necessary. The distribution of floor weight-bearing capacity shown in the figure below is compatible with either shielding option.


 
 

This material is based upon work supported by the National Science Foundation under Grant No. 0901016.


This page is maintained by Richard Jones.